Blackwall Reach Regeneration Project: Update Budget Report
Noting Blackwall Reach scheme delivery and funding update; approval for revision to capital budget for project.
Decision type: Non-key
Decision status: Recommendations Approved
Wards affected: Poplar;
Notice of proposed decision first published: 26/06/2016
Decision due: 26 Jul 16 by Cabinet
Lead member: Deputy Mayor and Cabinet Member for Regeneration and Air Quality
Contact: Corporate Director, Development & Renewal.
Consultation process
The Blackwall Reach Regeneration Project has been subject to extensive resident / stakeholder consultation during the master planning period, during partner procurement and subsequently during the outline pre-planning application design stage, and subsequently by Swan at detailed planning stages. Ongoing engagement has taken the form of regular newsletters and other communications, drop-ins and representative forums and steering groups etc, in addition to the dialogues on decant and property acquisitions. Following the confirmed CPO and other orders for the Phase 1-3 scheme areas, statutory and other communications have been issued, in line with good practice. No further consultation is required prior to this decision.
Has an Equality Analysis been carried out and if so the result of this Assessment?: No (decision sought does not significantly change or implement a new proposal).
What supporting documents or other information will be available?: None
Decisions
Agenda items
- 26/07/2016 - Cabinet Blackwall Reach Regeneration Project: Update Budget Report 26/07/2016