Approved Capital programme 20/2023 – additional projects
Further to the approval of the £668.079m
capital programme for 2020-2023 by the Mayor in Cabinet on 23rd
September 2020, funding sources have been identified for additional
projects for which approval is required. The additional projects
have progressed through the capital governance, to ensure that they
deliver value for money and agreed outcomes for our communities and
require approval to enable delivery in 2020-21. Funding options for
other priority programmes, for which funding sources have yet to be
identified will also be included. This may include approvals for
the disposal of identified assets to generate capital receipts
required for the delivery of the capital programme.
This report seeks further approvals for fully funded projects to be
added to the three-year capital programme.
Decision type: Non-key
Decision status: Recommendations Approved
Wards affected: (All Wards);
Notice of proposed decision first published: 12/10/2020
Decision due: 25 Nov 20 by Cabinet
Lead member: Deputy Mayor and Cabinet Member for Adults, Health and Wellbeing
Lead director: Corporate Director, Place
Department: Place
Contact: Jane Abraham, (Head of Capital Delivery) Email: jane.abraham@towerhamlets.gov.uk, Lindsey Gibson, (Executive Support Relationship Manager) Email: lindsey.gibson@towerhamlets.gov.uk, Nicole Layton, Executive Support Team Leader, Place Email: Nicole.Layton@towerhamlets.gov.uk.
Consultation process
N/A
Consultees
N/A
Has an Equality Analysis been carried out and if so the result of this Assessment?: Initial EqIAs form part of the PID approval process for individual capital programme areas. Full EqIAs are not required
What supporting documents or other information will be available?: N/A
Decisions
Agenda items
- 25/11/2020 - Cabinet Approved Capital programme 20/2023 – additional projects 25/11/2020
Documents
- Approved Capital programme 20/2023 – additional projects