Issue details
Liveable Streets Bow consultation outcome report
This item presents the results of the Bow
Liveable Streets project which was taken to public consultation on
Monday 29 June until Wednesday 29 July 2020.
This item seeks a decision on the next stages of the Liveable
Streets in Bow.
Decision type: Key
Reason Key: Expenditure or Savings of over £1 Million;
Decision status: Recommendations Approved
Wards affected: Bow East; Bow West;
Notice of proposed decision first published: 11/09/2020
Decision due: 25 Nov 20 by Cabinet
Lead member: Cabinet Member for Environment and Planning, Cabinet Member for Highways and Public Realm – (Job Share post as part of Social Inclusion and Public Realm portfolio)
Lead director: Corporate Director, Place
Department: Place
Contact: Inlia Aziz, (Assistant to Chief Executive's PA) Email: inlia.aziz@towerhamlets.gov.uk, Kristina Coxall, Project Centre Email: Kristina.Coxall@towerhamlets.gov.uk, Lindsey Gibson, (Executive Support Relationship Manager) Email: lindsey.gibson@towerhamlets.gov.uk, Chris Harrison, (Liveable Streets Technical Director) Email: Chris.Harrison@towerhamlets.gov.uk, Nicole Layton, Executive Support Team Leader, Place Email: Nicole.Layton@towerhamlets.gov.uk.
Consultation process
Four-week public consultation with the
residents, businesses and key stakeholders in the Bow Liveable
Streets area.
Consultation documents with paper survey were sent out to everyone
within the consultation area, as well as hosting a survey
online.
Queries were responded to via a dedicated email address.
Consultees
Public
Key Partners
Other Directorates
Has an Equality Analysis been carried out and if so the result of this Assessment?: Yes, an EqIA has been carried out for the project based on the results of the consultation. The EqIA will be updated as detailed design progresses.
What supporting documents or other information will be available?: N/A
Decisions
- 27/11/2020 - Liveable Streets Bow consultation outcome report
Agenda items
- 25/11/2020 - Cabinet Liveable Streets Bow consultation outcome report 25/11/2020
Documents
- Liveable Streets Bow consultation outcome report