Capital Programme 2020-21 to 2022-23
Further to the approval of the £702.413m
provisional capital programme for the period 2020-2023 by the Mayor
in Cabinet on 29th January 2020, a fundamental review of the
programme has been carried out to ensure that projects are
delivering value for money and agreed outcomes for our communities,
identifying where schemes could be reduced or deferred to minimise
the requirement for prudential borrowing. The report will ask for
approval of the revised Capital Programme 2020 to 2023.
Decision type: Key
Reason Key: Expenditure or Savings of over £1 Million;
Decision status: Recommendations Approved
Wards affected: (All Wards);
Notice of proposed decision first published: 10/08/2020
Decision due: 23 Sep 20 by Cabinet
Lead member: Cabinet Member for Resources and the Voluntary Sector
Lead director: Corporate Director, Resources
Department: Resources
Contact: Kevin Bartle, (Financial Consultant- formerly Interim Corporate Director, Resources & Section 151 Officer) Email: Kevin.Bartle@towerhamlets.gov.uk.
Consultation process
None
Consultees
None
Has an Equality Analysis been carried out and if so the result of this Assessment?: Initial EIAs form part of the PID approval process for individual capital programme areas (see above)
What supporting documents or other information will be available?: The Council’s draft 2020-21 budget – Cabinet 29th January 2020
Documents
- Capital Programme 2020-21 to 2022-23