HRA Capital Estimates Report
10/05/2013 - HRA Capital Estimates Report
DECISION
1. To agree the proposed works for the three year Decent Homes programme for 2013-14 to 2015-16.
2. To agree the proposed works for the 2013-14 non-Decent Homes programme, subject to satisfactory leaseholder consultation.
3. To adopt the reprofiled Capital Estimates for years 3, 4 and 5 of the Decent Homes Programme totalling £148.19 million, to bring the total Capital Estimate for the backlog and on-going Decent Homes programme to £181.37 million (paragraphs 5.1 to 5.5).
4. To adopt capital estimates for the Mainstream Capital Programme incorporating the schemes set out in Appendix 2, totalling £6,615,000, to be managed in accordance with resource availability under the HRA self-financing regime (paragraphs 5.6 to 5.12), and a contingency of £600,000 for urgent works (see paragraph 5.13).
5. To adopt a capital estimate of £500,000 to fund Overcrowding Reduction Initiatives as outlined in paragraph 5.14.
6. To adopt capital estimates for the Aids and Adaptations programme (£750,000), the Capitalisation of Voids (£1.5 million) and the Capitalisation of Fees and Salaries (£650,000) as outlined in paragraph 5.15.
7. To authorise the Assistant Chief Executive (Legal), to enter into all necessary documents to implement the decisions made in respect of this report.
Action by:
CORPORATE DIRECTOR DEVELOPMENT AND RENEWAL (A. DALVI)
(Service Head Strategy, Sustainability and Regeneration (J. Odunoye)
(Strategic Housing Manager, Development and Renewal (J. Coker)