Issue - decisions
Communities, Localities & Culture Directorate Capital Programme 2013/14
12/04/2013 - Communities, Localities & Culture Directorate Capital Programme 2013/14
DECISION
1. To include the schemes listed in Appendix A to the report within the Communities, Localities & Cultural Services Directorate’s 2013/2014 Capital Programme.
2. To adopt Capital Estimates (sum specified in estimated scheme cost column) for the schemes as outlined in Appendix A to the report.
3. To agree that where possible the Council’s Measured Term Contracts be used for the implementation of the Transport and Highways Works as appropriate.
4. To agree that where possible the landscape improvement works be let under the terms of the Landscape Framework Agreement for implementation as appropriate.
Action by:
CORPORATE DIRECTOR, COMMUNITIES, LOCALITIES AND CULTURE (S. HALSEY)
(Head of Transport and Highways (M. Cooper)