721-737 Commercial Road and 2-22 Lowell Street, Commercial Road, London
Decision:
The Committee RESOLVED that planning permission for the demolition of existing buildings and redevelopment up to 14 storeys to provide 319 residential units (9 x studio; 107 x 1 bed; 119 x 2 bed; 79 x 3 bed and 5 x 5 bed) and 675 sqm commercial (Class A2, A3, A4, B1, D1 and D2) space at 721-737 Commercial Road and 2-22 Lowell Street, Commercial Road, Londonbe GRANTED subject to:
A Any direction by the Mayor
B The completion of a legal agreement, to the satisfaction of the Assistant Chief Executive (Legal Services) to be completed within 3 month from the date of the Committee to secure the following:
- Affordable Housing provision at 35% of the habitable rooms with a 70/30 split between affordable rented/shared ownership.
- A contribution of £266,100 to mitigate the demand of the additional population on healthcare facilities.
- A contribution of £530,000 to mitigate the demand of the additional population on education facilities.
- A contribution of £219,000 towards Employment and training initiatives.
- A contribution of £35,000 towards TfL bus stop.
- A contribution of £20,000 to TfL signal booster to DLR or DAISY screen
- A contribution of £300,000 for Community initiatives (refurbishing and upgrading of nearby community centre.
- A contribution of £41,000 for upgrade works to Stonebridge Wharf
- ‘Car Free’ agreement
- LLIC
- TV/Radio reception mitigation
- Travel Plan
C That the Head of Development Decisions be delegated authority to impose conditions and informatives on the permission to secure the following:
1) Permission valid for 3 years
2) Submission of samples/details/full particulars
3) Submission of a Secured by Design Statement
4) Submission of a desktop study report for land contamination
5) Submission of details of site drainage
6) Submission of details of site foundations
7) Submission of an Investigation and remediation measures for land contamination
8) Provision of a minimum of 319 cycle spaces for the residential component of the scheme
9) Submission of a traffic management plan detailing all routes to be used by construction maintenance programmes and also detailing how sustainable travel to and from the proposed development will be provided amongst residents and staff working on the site.
10) Parking, access and loading/unloading, manoeuvring
11) No parking on site, other than in the basement car park
12) Vehicular access
13) Refuse and recycling facilities
14) Hours of Construction (8.00 am to 6.00 pm Monday to Friday 9.00 am to 5.00 pm on Saturdays and not at all on Sunday or Bank Holidays)
15) Power/hammer driven piling (10.00 am to 4.00 pm Monday to Friday)
16) Submission of full details of the proposed lighting and CCTV scheme.
17) Lifetime Homes
18) 10% Disabled Access
19) Renewable Energy Measures (at least 10% reduction in carbon dioxide emissions)
20) Applicant to use a 35 kilo Watt electrical combined heat and power plant.
21) Further archaeological work or historic building assessment as necessary, to establish the actual impact of development so an appropriate mitigation strategy can be implemented.
22) Any other conditions considered necessary by the Head of Development Decisions.
23) Applicant to enter into the relevant highways agreement with TfL and the Local Planning Authority to secure the construction, reconstruction, alteration, improvement or maintenance of the highway.
Minutes:
Mr Michael Kiely, Head of Development Decisions, introduced the site and proposal for the demolition of existing buildings and redevelopment up to 14 storeys to provide 319 residential units (9 x studio; 107 x 1 bed; 119 x 2 bed; 79 x 3 bed and 5 x 5 bed) and 675 sqm commercial (Class A2, A3, A4, B1, D1 and D2) space at 721-737 Commercial Road and 2-22 Lowell Street, Commercial Road, London.
Mr Terry Natt, Strategic Applications Manager, presented a detailed update report on the application. He reminded Members that the item had been deferred at the previous meeting to allow a daylight/sunlight assessment on the non-residential elements adjacent to the proposed site to be carried out.
The assessment was carried out using residential standards, as there were no published standards for non-residential properties. It was noted that if the Salmon Lane Evangelical Church had been residential, it would have passed the Average Daylight Factor (ADF) test. Therefore, the objection made on behalf of the Church had been withdrawn.
The Committee was informed that an assessment had been submitted by the residents of the Mission Building. It showed that the Mission Building would experience a loss of light to some windows. However, overall it was considered that the levels of daylight and sunlight would be adequate. As a result, the four letters of objection received from Mission Building residents had been withdrawn. Members asked for clarification on the levels of daylight and sunlight.
The Committee RESOLVED that planning permission for the demolition of existing buildings and redevelopment up to 14 storeys to provide 319 residential units (9 x studio; 107 x 1 bed; 119 x 2 bed; 79 x 3 bed and 5 x 5 bed) and 675 sqm commercial (Class A2, A3, A4, B1, D1 and D2) space at 721-737 Commercial Road and 2-22 Lowell Street, Commercial Road, Londonbe GRANTED subject to:
A Any direction by the Mayor
B The completion of a legal agreement, to the satisfaction of the Assistant Chief Executive (Legal Services) to be completed within 3 month from the date of the Committee to secure the following:
- Affordable Housing provision at 35% of the habitable rooms with a 70/30 split between affordable rented/shared ownership.
- A contribution of £266,100 to mitigate the demand of the additional population on healthcare facilities.
- A contribution of £530,000 to mitigate the demand of the additional population on education facilities.
- A contribution of £219,000 towards Employment and training initiatives.
- A contribution of £35,000 towards TfL bus stop.
- A contribution of £20,000 to TfL signal booster to DLR or DAISY screen
- A contribution of £300,000 for Community initiatives (refurbishing and upgrading of nearby community centre.
- A contribution of £41,000 for upgrade works to Stonebridge Wharf
- ‘Car Free’ agreement
- LLIC
- TV/Radio reception mitigation
- Travel Plan
C That the Head of Development Decisions be delegated authority to impose conditions and informatives on the permission to secure the following:
1) Permission valid for 3 years
2) Submission of samples/details/full particulars
3) Submission of a Secured by Design Statement
4) Submission of a desktop study report for land contamination
5) Submission of details of site drainage
6) Submission of details of site foundations
7) Submission of an Investigation and remediation measures for land contamination
8) Provision of a minimum of 319 cycle spaces for the residential component of the scheme
9) Submission of a traffic management plan detailing all routes to be used by construction maintenance programmes and also detailing how sustainable travel to and from the proposed development will be provided amongst residents and staff working on the site.
10) Parking, access and loading/unloading, manoeuvring
11) No parking on site, other than in the basement car park
12) Vehicular access
13) Refuse and recycling facilities
14) Hours of Construction (8.00 am to 6.00 pm Monday to Friday 9.00 am to 5.00 pm on Saturdays and not at all on Sunday or Bank Holidays)
15) Power/hammer driven piling (10.00 am to 4.00 pm Monday to Friday)
16) Submission of full details of the proposed lighting and CCTV scheme.
17) Lifetime Homes
18) 10% Disabled Access
19) Renewable Energy Measures (at least 10% reduction in carbon dioxide emissions)
20) Applicant to use a 35 kilo Watt electrical combined heat and power plant.
21) Further archaeological work or historic building assessment as necessary, to establish the actual impact of development so an appropriate mitigation strategy can be implemented.
22) Any other conditions considered necessary by the Head of Development Decisions.
23) Applicant to enter into the relevant highways agreement with TfL and the Local Planning Authority to secure the construction, reconstruction, alteration, improvement or maintenance of the highway.
Supporting documents:
-
Commercial Road, item 6.1
PDF 47 KB
-
Commercial RoadAppendix1, item 6.1
PDF 297 KB
-
Commercial RoadAppendix2, item 6.1
PDF 462 KB
-
Commercial RoadAppendix3, item 6.1
PDF 359 KB
-
Commercial RoadAppendix4, item 6.1
PDF 390 KB
-
Commercial RoadAppendix5, item 6.1
PDF 323 KB
-
Commercial RoadAppendix6, item 6.1
PDF 337 KB
-
Commercial RoadAppendix7, item 6.1
PDF 462 KB