IDF: Approval of the Allocation of CIL and S106 funding and Approval for the Adoption of a Capital Budget in Respect of the Following Projects: Brick Lane Regeneration Project; Route 108 Bow Enterprise Park Development Bus Service Enhancement; South
Meeting: 19/12/2017 - Cabinet (Item 5)
Additional documents:
- 5.7a Appendix A - SDB Initiation, Design & Public Consultation PID, item 5 PDF 189 KB
- 5.7b Appendix B - Route 108 PID Enhancement - Bow Enterprise PID, item 5 PDF 700 KB
- 5.7c Appendix C - Brick Lane Regeneration PID, item 5 PDF 375 KB
- 5.7d Appendix D - Middlesex Street Public Art PID, item 5 PDF 632 KB
- 5.7e Appendix E - Toynbee Hall PID, item 5 PDF 535 KB
- Webcast for IDF: Approval of the Allocation of CIL and S106 funding and Approval for the Adoption of a Capital Budget in Respect of a number of projects
Decision:
The Pre-Decision Scrutiny Questions and Answers were noted.
DECISION
1. To approve the allocation of £270,000 in Community Infrastructure Levy (CIL) funding to the proposals set out in the “South Dock Bridge: Initiation, Design and Public Consultation Phases”Subordinate Project Initiation Document (Sub-PID), which is attached to the Cabinet report at Appendix A and Table 1.
2. To approve the allocation of £440,000 in Section 106 (S106) funding to the proposals set out in the “Route 108: Bow Enterprise Park Development Bus Service Enhancement” Project Initiation Document (PID), which is attached to the Cabinet report at Appendix B and Table 1.
3. To approve the allocation of £1,143,405 in Section 106 (S106) funding to the proposals set out in the “Brick Lane Regeneration - Phase 2 Project Delivery” Project Initiation Document (PID), which is attached to the Cabinet report at Appendix C and Table 1.
4. To approve the allocation of £305,000 in Section 106 (S106) funding to the proposals set out in the “Toynbee Hall Refurbishment” Project Initiation Document (PID), which is attached to the Cabinet report at Appendix E and Table 1.
5. To adopt a capital estimate for the following projects detailed in Table 2 of the report:
a) Brick Lane Regeneration – Phase 2 Project Delivery Project Initiation Document (PID) attached at Appendix C and Table 2 (£1,143,405) of the report.
b) Middlesex Street Art Project Initiation Document (PID) which is attached at Appendix D and Table 2 (£304,326) of the report.
Action by:
ACTING CORPORATE DIRECTOR, PLACE (A. SUTCLIFFE)
(Divisional Director, Planning and Building Control (O. Whalley)
(Divisional Director, Growth & Economic Development (A. Scott)
(Supporting Divisional Director, Corporate Finance (S. Jones)
Minutes:
Note – Councillor Denise Jones left the meeting for the duration of the discussion of the Brick Lane Regeneration Project and Middlesex Street Public Art Project due to a Disclosable Pecuniary Interest. She returned for the next agenda item.
Councillor Rachel Blake, Cabinet Member for Strategic Development, introduced the report and passed over to the relevant Cabinet Members for each individual proposal.
The Mayor first discussed the proposal for the South Dock Bridge and the progress that had been made to date.
On Route 108 bus service enhancements, Councillor Amina Ali, Cabinet Member for Environment, noted that it was part of the Bow Enterprise development and that the associated s106 funding had originally been provided for public transport improvements.
In relation to the Brick Lane Regeneration Project, Councillor Joshua Peck, Cabinet Member for Work and Economic Development, explained that the area was a big visitor attraction for the Borough, it therefore needed a lot of care and investment. This proposal was the second stage of the project and included public realm improvements, wayfinding projects, artwork and more. This also included the Middlesex Street Art project which was listed as a separate item in the report.
On the Toynbee Hall Refurbishment Project, the Mayor explained that assistance was being sought from the Council which would help to underpin a number of services provided from that building.
The Mayor noted the Pre-Decision Scrutiny Questions and Answers. He then thanked officers for their work on these projects and on their efforts to ensure the most appropriate source of funding was used in each case. He agreed the recommendations as set out in the report.
RESOLVED
1. To approve the allocation of £270,000 in Community Infrastructure Levy (CIL) funding to the proposals set out in the “South Dock Bridge: Initiation, Design and Public Consultation Phases”Subordinate Project Initiation Document (Sub-PID), which is attached to the Cabinet report at Appendix A and Table 1.
2. To approve the allocation of £440,000 in Section 106 (S106) funding to the proposals set out in the “Route 108: Bow Enterprise Park Development Bus Service Enhancement” Project Initiation Document (PID), which is attached to the Cabinet report at Appendix B and Table 1.
3. To approve the allocation of £1,143,405 in Section 106 (S106) funding to the proposals set out in the “Brick Lane Regeneration - Phase 2 Project Delivery” Project Initiation Document (PID), which is attached to the Cabinet report at Appendix C and Table 1.
4. To approve the allocation of £305,000 in Section 106 (S106) funding to the proposals set out in the “Toynbee Hall Refurbishment” Project Initiation Document (PID), which is attached to the Cabinet report at Appendix E and Table 1.
5. To adopt a capital estimate for the following projects detailed in Table 2 of the report:
a) Brick Lane Regeneration – Phase 2 Project Delivery Project Initiation Document (PID) attached at Appendix C and Table 2 (£1,143,405) of the report.
b) Middlesex Street Art Project Initiation Document (PID) which is attached ... view the full minutes text for item 5