LBTH/THH Energy Company Obligation (ECO) Insulation Works on HRA Properties
Meeting: 31/07/2013 - Cabinet - Expired (Item 6)
6 Fuel Poverty and Insulation Works on HRA Properties (Project 2) PDF 98 KB
Additional documents:
Decision:
DECISION
1. To adopt a capital estimate of £4.063 million for fuel efficiency works on HRA properties to supersede the existing approvals of £1.809 million that are already incorporated into the approved budget, noting that the increase of £2.254 million is the Department of Climate Change grant funded element of the scheme.
2. To agree the proposed Fuel Poverty and Insulation Works on HRA Properties.
3. To agree the procurement of the contract, for insulation works on HRA assets, funded by DECC, the Council and ECO, through the RENEW Framework following a competitive tendering process.
4. To authorise the Corporate Director D/R in consultation with ACE Legal to award the contract to the successful contractor following completion of the competitive tendering process.
5. To authorise the Assistant Chief Executive (Legal Services) enter into all necessary documents to implement the decisions made in respect of this report.
Action by:
CORPORATE DIRECTOR, DEVELOPMENT AND RENEWAL (A. DALVI)
(Service Head, Housing, Regeneration and Sustainability (J. Odunoye)
Minutes:
The Mayor welcomed the report as another good piece of work and agreed the recommendations as set out.
RESOLVED
1. To adopt a capital estimate of £4.063 million for fuel efficiency works on HRA properties to supersede the existing approvals of £1.809 million that are already incorporated into the approved budget, noting that the increase of £2.254 million is the Department of Climate Change grant funded element of the scheme.
2. To agree the proposed Fuel Poverty and Insulation Works on HRA Properties.
3. To agree the procurement of the contract, for insulation works on HRA assets, funded by DECC, the Council and ECO, through the RENEW Framework following a competitive tendering process.
4. To authorise the Corporate Director D/R in consultation with ACE Legal to award the contract to the successful contractor following completion of the competitive tendering process.
5. To authorise the Assistant Chief Executive (Legal Services) enter into all necessary documents to implement the decisions made in respect of this report.