Parks and Open Spaces Capital Improvement Programme
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
Purpose:
The Parks Capital Improvement programme will
enable investment into parks and open spaces. Investment
improvements will include:
- Improvements to outdoor sports amenities
- Upgrades to parks and open spaces
- Upgrades to playground equipment in parks and open spaces
including a number of Council managed housing estate playground
areas
Decision:
DECISION
1. Approve the Parks and Open Spaces Capital Programme and the allocation of Capital funding from s106. The estimated amount requested is £5,246,000 (including £627,000 reallocation of budget provision within the existing programme) and is subject to funding being confirmed through the Capital Governance Process.
2. Authorise the Corporate Director of Communities, after consultation with the Corporate Director of Resources (or their nominee) to agree and enter into the terms and conditions of any agreements required to implement the programme.
3. That a review is undertaken by the Parks Service that identifies any additional council play equipment that should be renewed or replaced on health and safety grounds, setting recommended dates for such action.
4. That a report is brought back to the Mayor in Cabinet by the Corporate Director of Communities at the earliest opportunity identifying any such play equipment along with the costs of renewal and forming part of a structured, risk-based renewal and replacement rolling plan that ensures that health and safety risks in relation to children's play equipment is properly mitigated in a planned way going forward.
5. To note the health and safety consideration in Paragraph 3.10 of the report and risk management section in 5.5 of the report.
6. To note the Equalities Impact Assessment considerations as set out in Paragraph 4 of the report.
Action by
INTERIM CORPORATE DIRECTOR, COMMUNITIES (R. MISTRY)
Head of Arts, Parks and Events (C. Boyd)
Report author: Catherine Boyd
Publication date: 01/12/2023
Date of decision: 29/11/2023
Decided at meeting: 29/11/2023 - Cabinet
Accompanying Documents: