Decision details
Blackwall Reach Regeneration Project: Update Budget Report
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
Purpose:
Noting Blackwall Reach scheme delivery and funding update; approval for revision to capital budget for project.
Decision:
DECISION
1. To note the update on scheme delivery and the Council’s CPO in paragraphs 3.2.1 to 3.2.12 of the report.
2. To note the update on actual and projected expenditure, scheme funding and potential overage in paragraphs 3.3.1 – 3.3.14 of the report.
3. To approve an increase in the capital budget for the scheme to £20.3 million, as set out in paragraphs 3.3.2 to 3.3.8 of the report.
Action by:
CORPORATE DIRECTOR, DEVELOPMENT AND RENEWAL (A. DALVI)
(Housing Regeneration Manager (N. McGowan)
(Service Head, Strategy, Regeneration and Sustainability (J. Odunoye)
Report author: Corporate Director, Development & Renewal
Publication date: 28/07/2016
Date of decision: 26/07/2016
Decided at meeting: 26/07/2016 - Cabinet
Effective from: 05/08/2016