Decision details
Housing Revenue Account Budget Report 2016/17
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
1. Approve the Tower Hamlets Homes Management Fee 2016/17;
2. Approve the Housing Revenue Account Draft Budget 2016/17; and
3. Approve 2016/17 housing capital estimates.
Decision:
DECISION
Revenue
1. To approve the draft 2016/17 Housing Revenue Account budget as set out in Appendix 1.
2. To approve the draft 2016/17 Management Fee payable to Tower Hamlets Homes (THH) of £33.376 million as set out in Table 7 in section 10.
3. To note that under the Management Agreement between the Council and THH, THH manages delegated income and expenditure budgets on behalf of the Council. The principal delegated income budgets are for rental income and service charges, and the major item of delegated expenditure is repairs and maintenance. In 2016/17, THH will manage delegated income budgets totalling £88.512 million, and delegated expenditure budgets of £24.208 million.
4. To note the HRA Medium Term Financial Plan (2016/17 to 2020/21) outlined in Appendix 2.
Capital
1. To adopt a capital estimate of £2 million in relation to external works on priority blocks, as outlined in paragraph 13.3.
2. To adopt a capital estimate of £11.5 million to fund newly arising Decent Homes works as outlined in paragraphs 13.4.
3. To adopt a capital estimate of £3.6 million in relation to Mechanical and Electrical schemes Initiatives as outlined in paragraph 13.5.
4. To adopt a capital estimate of £4 million in relation to Fire Risk Assessment as outlined in paragraphs 13.6.
5. To adopt a capital estimate of £1 million to fund Overcrowding Reduction Initiatives as outlined in paragraph 13.7.
6. To adopt capital estimates for the Aids and Adaptations programme (£750,000), the Capitalisation of Voids (£1.5 million) and the Capitalisation of Fees and Salaries (£650,000) as outlined in paragraph 13.8.
7. To adopt a capital estimate of £200,000 in order to maintain a contingency for urgent works of £1 million, as outlined in paragraph 13.9.
Action by:
CORPORATE DIRECTOR, DEVELOPMENT AND RENEWAL (A. DALVI)
(Service Head, Resources (C. Holme)
(Finance Business Partner (P. Leeson)
(Senior Accountant (HRA and Capital) (K. Ball)
Report author: Corporate Director, Development & Renewal
Publication date: 04/02/2016
Date of decision: 02/02/2016
Decided at meeting: 02/02/2016 - Cabinet
Effective from: 12/02/2016
Accompanying Documents: