Decision details
New Electric Vehicle Charging Delivery Plan 2021-2025 and funding towards new public charging points.
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
Part 1: Approval pf new EV Charging Delivery
Plan de 2021-2025. This document sets out our approach to charging
points delivery over the next 5 years.
Part 2: Approval for £500,000 of CIL funding to facilitate a
£1,500,000 bid to the OZEV (Office for Zero Emission
Vehicles). The total of £2,000,000 would funding the
installation of 250 public fast chargers (7kw-22kw) across the
borough by the end of March 2023 as set out in the EV Charging
Delivery Plan.
Decision:
The Pre-Decision Scrutiny Questions and officer responses were noted.
DECISION
1. To approve the Electric Vehicle Charging Delivery Plan and targets for delivery by 2025.
2.
To adopt a capital estimate of £329,840 to be
included in the capital Programme 2021/22, and earmark
£82,000 from the Transportation Service Streetscene Enhancement Revenue budget to deliver
150 Street Lighting Column Electric Vehicle Charge Points by 31
March 2022.
3. To approve £500,000 of CIL funding as a match contribution towards a bid for £1,500,000 which will be released subject to the bid being successful.
4. To approve the use of the available procurement channels to procure 150 slow charge lamp column charging points and 250 fast chargers.
Action by:
CORPORATE DIRECTOR, PLACE (A. SUTCLIFFE)
(Director of Public Realm (D. Jones)
(Principal Transport Planner (M. Chibou)
Report author: Nicole Layton
Publication date: 24/09/2021
Date of decision: 22/09/2021
Decided at meeting: 22/09/2021 - Cabinet
Effective from: 02/10/2021
Accompanying Documents: